Wednesday, November 1, 2017

Surprising - Palmetto Bay's contracted Irma debris pickup ends as of 10/29 for lack of a second

I have to say that I am very surprised. Palmetto Bay has backed out of Irma storm collection and area restoration.  The Palmetto Bay Contractors had ceased collection as of Wednesday, October 25, 2017.

The request from staff to extend the collection failed for lack of a second at the Special Council Meeting held Monday, October 30, 2017.  This meeting was specially called due to the time sensitive nature of the item to consider extending the debris removal services (CLICK HERE - to view the agenda items).

Yes, the debris pick up was not without its frustrations, but overall, our hired crews worked well in complementing the County efforts at debris removal. The Contractor satisfied the contract - the fact was that the level of debris was actually greater than estimated, which to me meant that it was even more important that we supplement the pick up rather than sit back and place the entire burden on the County. 

The renewal failed for lack of a second at the meeting:

The two-team collective effort is now down to one.  Miami-Dade County is now on its own and solely responsible for continued debris removal, to finish the first sweep and complete any additional clean up or specialty sweeps (including stump or hanging branch removals).  Our efforts died as no council member would second the resolution after Council Member Larissa Siegel Lara moved the item forward - and noting that she stated an intention to enter into a compromise, rather than a full approval of the proposed extension.

Please click the "Storm Restoration" label, and then scroll down to view some of my past updates regarding our efforts to get Palmetto Bay back to pre-Irma status.  

Our crews collected debris over a mere 29 days. Irma struck our area on September 10/11. They  were contracted to start debris removal at the Saturday, September 30, 2017, Special Council meeting.  The Crews started at 2:30 PM on that same day.  Our contracted crews  removed nearly 120,000 cubic yards of debris - as can be seen piled high at the east end of Coral Reef Park or at the second debris station off 168 and Old Cutler Road.

I was told that our crews averaged about 6,000 cubic yards per day, the first two weeks. Toward the end, the crews were averaging 5,000 cubic yards daily. 

Palmetto Bay is now out of the storm debris removal efforts, turning the responsibility back over to Miami-Dade County to complete the efforts. 

The crews will complete their contracted duties of grinding the piles located at both our debris collection points.  The ground debris will then be disposed of at a County/FEMA approved site.

I commend the work of the contracted crews who did work seven days a week to work with Miami-Dade County to remove debris from Palmetto Bay.  This effort greatly sped up the debris removal.  The village staff who were diverted to this effort (which included monitoring) will now return to their normal assignments, unless they are required to remain at the debris collection sites.

No comments:

Post a Comment