This project affects both Pinecrest and Palmetto Bay.

The Florida Department of Transportation (FDOT) District Six is
developing the design for a safety improvement project along SR 5/US 1 at
Howard Drive/SW 136 Street, in Miami-Dade County. The scope of work for this
project is listed in the project fact sheet (
CLICK HERE to view online).
Construction is expected to
begin in November 2020 and last about four months. The estimated construction
cost for this project is $385,520.
Work is expected to begin in November 2020 and last about four months.
Please note that the construction duration is subject to change.
Project Identification Number: 439984-1-52-01