US 1 ROAD WORK UPDATE

Pinecrest Parkway Improvements by FDOT to be Completed in May 2013 (Information provided from Pinecrest e-news)

Commuters should have noticed the roadway work that started August 20th.  The inside left turn lane along northbound US 1 at the intersection of SW 136 Street will be closed daily from 9 a.m. to 3:30 p.m. while the contractor rebuilds the center median. This work is scheduled through Friday, August 24th. The outside turn lane will remain open at all times.

One outside lane may be closed at times along US 1 from SW 132 Street to SW 102 Street while the contractor replaces sections of sidewalk and curb and gutter. The closure will be from 9 a.m. to 3:30 p.m. Monday through Friday. At least one travel lane will remain open at all times.