Estimated completion date of the project is the second week of December
2015
Start date of the project has been pushed back to October 5, 2015 to
allow for further community out reach
Project completed in three (3) Phases
Phase 1 Construction - SW 152nd ST from SW 83rd AV to SW 82nd AV
Road Closure – 9:30am – 6:30pm SW 152nd ST closed eastbound and westbound from SW 83rd AV to SW 82nd AV
Intersection of SW 152nd ST and SW 82nd AV open to vehicular traffic traveling N and S on SW 82nd AV and east of SW 82nd AV on SW 152nd ST daily during phase 1
Phase 2 Construction - SW 152nd ST from SW 80th AV to SW 82nd AV
Road Closure – 9:30am – 6:30pm
SW 152nd ST closed eastbound and
westbound from SW 80th AV to SW 82nd AVIntersection of SW 152nd ST and SW 82nd AV open to vehicular traffic traveling N and S on SW 82nd AV and west of SW 82nd AV on SW 152nd ST daily during phase 2
Phase 3 Construction – Intersection of SW 152nd ST and SW 82nd AV
Road Closure – Proposed work to
be scheduled on a Saturday with complete closure of intersection, if
intersection needs to be closed on a weekday it will be closed from 9:30am –
4:30pm during phase 3 but it is expected
that the work in phase 3 will be completed in a two day time frame.
There will be no open trenches at the end of the work day and all roads
will be open to vehicular traffic by 6:30 p.m. daily.